Foundation Is Coming In

So it is always good to have flexible subs.   When you find em, let em have some dates and come up with contingency for early start or late start.

We anticipated Permit Data of August 27, 2015 but got it on August 18, 2015.   The foundation contractor can start early so Tuesday we are starting with the Layout.

Today I cleared some area for a dumpster.

So when action starts.

1.  Get a porta potty on site
2.  Get a Dumpster
3.  Apply for your GIS address so you can
4.  Get Power from Chelco

And always make friends with a neighbor who will let you have power to your site until the temporary service is set up.

Wish us luck.....we are about to go vertical.